From appointing an architect to moving into the finished home, a substantial heritage renovation in Melbourne commonly takes two to four years. A straightforward rear addition may be quicker. A project with a basement, major temporary works, a pool or a difficult planning pathway may take longer.
The honest answer is not one number. It is a program made from overlapping design, planning, consultant, approval, procurement and construction stages.
The ranges below are a planning guide, not a promise. Council workload, design changes, consultant coordination, neighbour matters, latent conditions and product lead times can all move the result.
Project type
Pre-construction
Construction
Indicative total
Straightforward rear addition with limited restoration
9 to 15 months
12 to 16 months
21 to 31 months
Substantial whole-home heritage renovation and addition
12 to 20 months
16 to 24 months
28 to 44 months
Heritage renovation with basement, pool and complex site works
16 to 26 months
24 to 36 months
40 to 62 months
Some activities can overlap, so the total is not always the simple sum of every line item. The ranges also assume decisions are made within reasonable timeframes and the project proceeds without a major redesign.
Brief and concept design
Allow approximately two to five months, depending on how quickly the brief, budget and design direction settle.
This stage may include:
The budget should be reviewed before the preferred concept becomes difficult to change.
Planning and heritage approval
Allow approximately four to 12 months for many substantial proposals, but treat this as highly project-specific.
The period may include:
Not every Heritage Overlay application is publicly notified. The architect or planner should confirm the actual pathway.
Design development and construction documentation
Allow approximately five to 10 months for a substantial architectural home.
This is where architecture, interiors, structure, civil and hydraulic design, mechanical services, electrical and lighting, landscape, pool and specialist systems are coordinated.
The stage often takes longer than clients expect because the work is not simply “drawing more detail”. It is resolving how multiple consultant packages fit together.
Pricing, contract and permits
Allow approximately two to five months, depending on the procurement pathway and the quality of the documentation.
Competitive tender may require tender preparation, builder queries, comparison and negotiation. A negotiated tender may have been pricing the project progressively, but still needs final trade coverage, scope reconciliation and contract negotiation.
Building-permit work may overlap with final documentation and pricing, subject to the approval strategy.
Retention and temporary support
Keeping the original home while constructing around, behind or beneath it introduces stages that do not exist on a clear new-home site.
The team may need to:
Basements
A basement can add significant time through piling, retention, excavation, spoil removal, dewatering, waterproofing, concrete structure and restricted access.
The basement also affects everything above it. A delay in the substructure can delay the entire home.
Specialist restoration
Tuckpointing, ornate plaster, leadlight, period joinery, slate roofing and specialist metalwork depend on a smaller trade pool. Availability and sample approval need to be built into the program.
Client decisions and design changes
Late changes affect more than the selected item. A change to a tap may affect plumbing rough-in. A change to stone may affect shop drawings, structure and joinery. A change to a window may affect planning, energy, structure and cladding.
The project needs a clear decision schedule, not just a construction schedule.
Good programming identifies tasks that can proceed together without creating rework.
Examples may include:
The consultants must still control revisions carefully. Overlap saves time only when the team understands which information is stable and which remains subject to change.
TCON prepares a project-specific pre-construction program and then a detailed construction program. The program identifies approvals, pricing, consultant information, client decisions, long-lead procurement and site sequence.
The objective is not to publish the shortest possible duration. It is to establish a sequence that the design team, client, trades and builder can actually deliver.
If you have concept or planning drawings for a heritage project, TCON can prepare an early program showing the likely approval, documentation, pricing and construction sequence. That is more useful than applying a generic renovation duration to a complex home.
Building with TCON
Considered architecture demands considered building. Building with TCON is a complete account of how TCON works. Available on request and reviewed personally by Tim before release.
Request a copy of Building with TCON.